WEEK 6: CAD drawing submitted for fabrication

The week after presentation, helped me to address very important details regarding the current insulator and rail. Also, it helped few modification on the current pick up mechanism to pivot about a joint. I have addressed those details as shown in the figure below. Using SolidWorks, I was able to calculate the tolerance angle as the current pick up mechanism is raised for a maximum on 1 in. a 10 degree angle will be used on the top pivot point.  Additionally, I have sent the final drawing to Turpo Manufacturing company for fabrication. They will be machining some on the parts on this mechanism in exchange of advertising. finally I'll be working on the unistrust channels which will hold our current rail.

Week 5 (February 6,2019):Latest current pick up mechanism and current rail design

For the past week, the team have modified the current rail and the current pick up mechanism. The figure above represent last year design. the figure above is the latest design The figure on the right is the mechanism that will make contact with the electric current rail. the legs (L-shaped) are design to fit the the width of the overall Guideway track.